Home » How to size a Thyristor

How to size a Thyristor

It is first necessary to recognise whether the application is single or three-phase. For single phase (1PH) you can use the calculation: total load (in watts) over the load voltage (L to N or L1 to L2) to give the current value (I = P/V). . .

It is first necessary to recognise whether the application is single or three-phase. For single phase (1PH) you can use the calculation: total load (in watts) over the load voltage (L to N or L1 to L2) to give the current value (I = P/V).

For example, load is 12kW and the voltage (L to N) is 240V giving a current of 50A. We normally add a safety margin of 15-20% to this nominal current in selecting a thyristor power controller to ensure we allow for any fluctuations in voltage supply or temperature, etc. This means we are not switching at the unit’s maximum which results in a longer thyristor life.

Three phase (3PH) systems are normally used for larger power consuming loads. The voltage between any two legs of a three-phase system is a sinusoidal AC waveform but the voltage waveform between each successive pair of legs will be displaced in time by 120 electrical degrees from the other two. This corresponds to 6.67 milliseconds for a 50Hz system. Assuming the load is 12kW but connected to 3 phase we would have 12000 watts over the voltage, times by the square root of 3 (1.73) for convenience. So the current would be 12000 / 415 × 1.73 = 16.8 amps.

View our Thyristor range to see all our product offerings.

Our Address
Unit 9 Harvington Business Park, Brampton Rd, Eastbourne, BN22 9BN, UK
Need Help?
We aim to reply to email enquiries within 20 minutes (during normal working hours).
CD Automation UK Limited © Copyright 2026. All Rights Reserved.

Thanks for your submission!

What happens next?

This isn't an automated product-selection tool.

One of our team will look at the information you've provided and review the application from an engineering point of view.

We may come back with a few questions, but we'll normally be looking at things such as:

  • The type of electrical load
  • Supply and current requirements
  • The most appropriate firing method
  • REVO-S, REVO-C or multi-loop architecture
  • Diagnostics and monitoring requirements
  • PLC and communications
  • Opportunities to simplify the design
  • Future machine standardisation

No lengthy specification needed.

Just give us enough information to get the conversation started.

Prefer to talk?

Call us on 01323 811100

CD Automation UK

Industrial power control. Backed by people who understand the application.

Please send me this document

🎉 Thank you! Your download is ready.

You can access your PDF now by clicking the link below:
Inside, you’ll discover the 5 common mistakes that can affect machine performance and how to avoid them to save time, reduce downtime, and improve product quality.

🎉 Thank you! Your download is ready.

You can access your PDF now by clicking the link below:
This paper explores how integrated thyristor power and temperature
control improves heating consistency, energy efficiency, and reliability,
helping UK manufacturers reduce downtime, extend equipment lifespan,
and shift from reactive to predictive maintenance.